Guide · Updated 1 November 2026 · 6-minute read
Do you own a home in Ticino and have received a letter in Italian asking for a ‘rapporto di sicurezza’? This is the electrical safety certificate required by Swiss law. This guide explains what it is, who carries out the inspection, how long you have and what to do, step by step.
The safety certificate is defined in the Swiss federal Ordinance on Low-Voltage Installations (NIV/OIBT, SR 734.27). It confirms that the installation meets the safety requirements and does not interfere with other equipment. It includes a measurement and test report.
Swiss law places the responsibility on the owner: keep the installation in good condition, have defects rectified without delay and present the safety certificate on request. Keep the latest certificate with your property deeds and papers.
The interval depends on how the building is used: the higher the risk, the more frequent the inspection. Swiss law sets intervals of 1, 3, 5, 10 or 20 years. The most common cases:
| Building or installation | Inspection every |
|---|---|
| Houses and apartments (including those in condominium buildings), underground car parks of residential buildings | 20 years |
| Small shops and service businesses (hairdressers, phone shops…), offices, workshops | 10 years |
| Restaurants, bars, takeaways, hotels, schools and other places where many people gather | 5 years |
| Whole apartment let as a holiday rental (e.g. Airbnb); if only single rooms are let, 20 years still applies | 5 years (like a hotel) |
| Older installations wired to the former ‘Schema III’ (TN-C system: neutral and protective conductor combined) | 5 years, until they are replaced |
| EV charging points in publicly accessible areas | 5 years |
| Wallbox (home charger) at home or in a private car park | same as the building it is in |
The interval is set by the ordinance according to how the premises are actually used; it is stated on the safety certificate and recorded by the network operator. It runs from the final inspection (new installation) or from the last periodic inspection.
The owners of a house built in the 1990s receive the letter requesting its 20-year inspection. The inspector finds typical defects: a damaged garden socket, a junction box without its cover and a broken earth connection. The electrician rectifies them in one day and the inspector issues the certificate – all without the owners having to travel to Ticino.
Ask the network operator for an extension in good time, with a short reason (for example: no inspector available, or a renovation already planned). The ordinance allows an extension of up to one year after the deadline. Under an ESTI exemption issued in December 2023 and valid for six years, network operators may grant, case by case, up to two years if the request is well justified.
If the certificate has still not been submitted after two reminders, the network operator passes the case to ESTI, which orders the inspection.
If you are planning to rewire the property, say so straight away: ESTI may consider an extension if you provide a list of defects, a final building permit or other supporting documents. Dangerous defects must be rectified immediately in all cases.
For installations with a 10- or 20-year interval, every change of ownership triggers a periodic inspection if the last one is more than 5 years old. If you are buying, ask to see the latest safety certificate early on: any defects will cost money to put right and can be raised in negotiations.
Request a free quote Call +41 91 972 20 20
See also: Our electrical services
Yes. Swiss law requires the owner to have the installation inspected at the end of the inspection interval and to submit the safety certificate to the network operator.
No, the obligation lies with the owner or the property management. If you have made changes to the installation yourself, inform the owner.
No. Swiss law separates inspection and installation work: the periodic inspection is carried out by an independent company, and defects are rectified by an electrical contractor.
The owner bears the cost, which depends on the size of the installation and the number of circuits. Ask the inspection company for a quote. If you wish, we arrange the external inspector and send you a quote for the remedial work as soon as the list is available.
In a condominium (a building in shared ownership – PPP in Italian, STWEG in German, PPE in French), the administrator (amministratore) arranges the inspection of the common areas (stairwell, car park, plant rooms), and the costs are usually shared according to each owner's share, unless the condominium regulations say otherwise. The installation inside each unit is the responsibility of its owner. In rented property, the inspection and remedial work are the landlord's responsibility, not the tenant's, except for damage caused by the tenant.
Ask the network operator or the company that did the last inspection for a copy. If it cannot be found, a new certificate will be issued after the next inspection.
The network operator writes at least 6 months before the deadline. On a justified request, the network operator may extend the deadline case by case, currently by up to two years.
Il vostro voto ci aiuta a migliorare le guide.
Leggiamo ogni messaggio. Il commento non viene pubblicato. Privacy
Invio non riuscito. Riprovate o scriveteci a info@mcelectrics.ch.
Grazie, abbiamo ricevuto il vostro voto.
Vi abbiamo aiutato anche con un lavoro? Una recensione su Google aiuta altri clienti a trovarci.
Lasciate una recensione su Google
Written by the technical office of MC electric's SA, electrical contractors holding a general installation permit and an inspection permit issued by ESTI, based in Pregassona (Lugano). Technical review: Walter Cubisino, master electrician with the Swiss federal diploma (eidg. dipl. Elektroinstallateur).
Note: this guide summarises the rules in force on 1 November 2026 and is not a substitute for individual advice. A full revision of the ordinance is under way; we will update this page when the rules change.